Monday morning there was just a slab of concrete waiting for the eye clinic to be built on it.
Most of Monday was prep work for getting the exterior walls put together and then raised. We got the far walls ready and will raise them first thing on Tuesday.
The slab on Tuesday morning waiting for everyone to get back to work.
The far wall went up in two pieces and was quite amazing.
Another section of wall up right before lunch.
Two more sections went up after lunch.
At the end of the day Tuesday we had raised five sections of exterior wall. We are on schedule to have the rest of the exterior walls up by end of day tomorrow and then start on interior walls and the trusses for the roof.
Wow! This is just amazing. It make my heart just full!
ReplyDelete